RTA logo Lake Line & South Main Line Track Improvements - Green Line

Description

This project will provide for the replacement of ties, track fasteners, footwalk, and incidental signal and traction power in addition to track improvements. This will be on the Green Line┐s Lake Line, between Clinton and Ashland, and the South Main Line, between Tower 17 and 35th Street.

 
Status
Service Board:Chicago Transit Authority
Program Category:Modernization
Budget:$70,000,000
Overall Status:Design
Budget Status:On Budget
Schedule Status:On Schedule
Current Activities:Kiewit Infrastructure Company was awarded the design‐build contract at the CTA┐s March Board meeting on 03/13/2019. The Construction Manager for the project will be STV Incorporated. CTA Forces completed advance track and structural work in the Lake Line project area. CTA Forces continued performing advance structural work in the South Mainline project area. CTA will issue an NTP to Kiewit for the design‐build contract. It is anticipated that Kiewit will submit in Q2‐2019 all of the preliminary design submittals, perform the initial LIDAR survey, rail‐grinding work on both the Lake Line and South Mainline, and begin the tie replacement work on the Lake Line of the project. CTA will also issue NTP to STV for the construction management task order. CTA Forces will complete the advance structural work in the South Mainline project area.
Information Updated:July 2019
 