Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2023 Project Management Oversight report. 

?

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Mode Sort descending 2024 Funding 2024-2028 Funding Status
+ Pace River Division Electrification/Expansion Support Facilities & Equipment Bus $75,999,933 $142,827,620 Behind Schedule

Project Details

Description
This project is for architectural and engineering services that will provide pre-design services, geotechnical engineering, land surveys, traffic studies, existing facilities testing and evaluation and feasibility studies. It will also include design and construction administration, inspections and project oversight. Pace intends to expand and improve its existing River Division bus garage onto newly acquired property south of the existing garage. It will be designed to accommodate storage, servicing,maintenance, and associated program areas for an additional 75 buses, 26 paratransit and 6 nonrevenue vehicles in addition to other improvements to modernize the existing facility. Once the A/E design is completed, construction will follow.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $75,999,933 $66,827,687 $142,827,620
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $75,999,933 $66,827,687 $142,827,620

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$36,110,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace has entered into a contract for Architectural and Engineering services for pre-design and design services. The contractor completed the pre-design activities, and final pre-design report was submitted to Pace. The adjacent property acquisition has been completed. Pace is undertaking an electrification study that will inform the design changes needed to make this facility compatible with an electric bus fleet. The design activities are currently on hold pending the recommendations from this study. Pace will need to revise the initial 30% design to incorporate future electrification components before activities resume with the designer.

Last Updated 12.14.2023

+ Pace Purchase 7-passenger Vanpool Vehicles Rolling Stock Bus $0 $0 On Schedule

Project Details

Description
Vanpool Vehicles - Pace plans to purchase 164 replacement 17'-20' vans including associated equipment and services (Buy America audit and inspections) for vanpool services.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$13,899,800
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The vans will be utilized in the six county Pace service area. To date a total of 25 vans have been ordered, all have been received. Pace has executed a contract to install OEM passenger running boards on the first order of 25 vans. All the running boards have been installed and are in the active fleet. Pace continued to work on an action plan for ordering more vehicles based on projected needs under a separate contract. This will be the final update on this project.

Last Updated 12.14.2023

+ Pace Fixed Route Electric Buses Rolling Stock Bus $0 $78,009,128 On Schedule

Project Details

Description
Replace 52 diesel buses with electric buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections).
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $72,614,500 $72,614,500
State $0 $0 $5,394,628 $5,394,628
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $26,192,311 $0 $78,009,128 $104,201,439

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$28,810,673
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contract was executed, and the vendor provided Pace with an updated production schedule due to previous supply chain issues and long lead time items. Deliveries of the buses were delayed and now expected to begin in Q1-2024. Pace executed a change order to purchase an additional two buses, bringing the total to 22 electric buses. Delivery of charging equipment began this quarter.

Last Updated 12.14.2023

+ Pace Transit Signal Priority (TSP) Electrical, Signal & Communications Bus $0 $0 On Schedule

Project Details

Description
Transit Signal Priority Integration - TSP implementation along priority corridors as part of the Regional Transit Signal Priority Implementation Program. Pace plans to deploy TSP along nine additional corridors at approximately 300 signalized intersections. The corridors include: 159th Street, Sibley Boulevard/147th Street, Roosevelt Road, Cicero Avenue, 95th Street, Grand Avenue (Lake County), Cermak Road, I-90 Transit Corridor Access Intersections and Halsted Street. This form represents the portion of the project funded with PAYGO in 2024. Years 2021-2023 of TSP related projects are funded with ICE funds as shown in Exhibit I.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,314,071 $0 $0 $4,314,071

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$14,031,402
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The vendor received the permit to implement TSP system along 58 signalized intersections of Dempster Street from IDOT. Systems integration testing were completed at 47 of the 58 signalized Dempster intersections was completed and railroad crossings field tests/data analysis completed at various locations along Dempster. TSP installation along Dempster St. in Evanston is in process and will continue thru Q2-2023. The vendor completed construction and systems implementation along Grand Ave. in a previous but this quarter acquired IDOT District 1 approval and permitting for EOS deployment along Grand and other corridors. Deployment and initial testing of TSP along Roosevelt Rd. was completed and the vendor is currently demonstrating the information to IDOT Dist. 1. TSP deployment along 147th St. was completed and Pace acquired permits for 95th St. with construction continuing through 2023. Permit acquisition activities continues for Rand, Cermak, and 159th w

Last Updated 12.14.2023

+ CTA 2022 - Bus Maintenance Rolling Stock Bus $0 $0 On Schedule

Project Details

Description
Funding for this project will provide for an ongoing capital maintenance program that consists of tasks necessary to keep buses in service through systematic inspection, detection, and prevention of incipient failure. CTA’s scheduled maintenance program consists of planned preventive maintenance work to maintain bus performance. While major overhaul work is performed on a mid-life cycle basis, additional focused maintenance work is required at certain intervals, outside of the mid-life overhaul, during the life of buses. When certain maintenance tasks are needed to repair or replace, before it reaches its end of useful life and failing with an increased frequency, specific component campaign work is conducted.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $56,000,000 $0 $0 $56,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$36,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Bus maintenance activities began on this project during this reporting period. Major rehabilitation elements will include, but not limited to, body work, vehicle wiring, and brakes.

Last Updated 12.14.2023

+ Pace Intelligent Bus System (IBS) Electrical, Signal & Communications Bus $0 $0 Behind Schedule

Project Details

Description
Intelligent Bus System - Project includes replacement Automatic Passenger Counter equipment (450), routers (600), Apollo cameras (650), IBS servers (8) & software, Storage Area Networks (2), dispatch radios (22), mobile radios (70), Integrated Vehicle Logic Unit Mobile Data Terminals (800), Tate data radios (800), Motorola voice radios (800), and data tower Radio Network Controller equipment (11).
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,250,000 $0 $0 $2,250,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$2,250,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace began activity of this project during this reporting period. This will be for automatic passenger counters on fixed route buses. Activities have just started and expected to ramp up in Q1-2024.

Last Updated 12.14.2023

+ CTA Purchase up to 70 Electric Buses and up to 9 Charging Stations Rolling Stock Bus $0 $0 On Schedule

Project Details

Description
Purchase up to 70 Electric Buses and up to nine Chargers - Bus funding provides for a future order of up to 70 40-foot battery-powered, zero-emission, all-electric, fully accessible, public transit buses with en-route charging capabilities. CTA will retire up to 70 1000-Series New Flyer buses that are over 14 years old. Turnkey project to procure Electric buses and associated charging infrastructure.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$71,991,905
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The charging stations were received and installed and reached substantial completion in January 2021. In Q4-2021, seventeen (17) production buses were completed and delivered to CTA. The installation of revenue fare collection systems, communication equipment, network systems were completed in Q2-2022. A total of twenty-three (23) buses were delivered. Nineteen (19) are in service and four are being used at the 74th Garage for operator training. In this reporting period, CTA has exercised an option for an additional twenty-two (22) buses. CTA’s Infrastructure department is working with Bus Engineering to finalize the budget breakdown and scope for the 103rd Garage.

Last Updated 12.14.2023

+ Pace South Campus Project - Markham Support Facilities & Equipment Bus $0 $0 Behind Schedule

Project Details

Description
This project will provide for construction, project management oversight, project administration, and any associated equipment and services for the Pace South Campus project. New facilities will be built on a 22-acre site that is situated next door to Pace’s South Division (2107 W. 163rd Place) Garage in Markham, Illinois, which is already owned by Pace. The purpose of this project is to consolidate certain operational functions currently operating at each garage into one location.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$35,215,466
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Notice to Proceed for construction has been issued in January 2022. Construction activities are in progress. Construction and procurement activities continue. The Acceptance facility gas service is complete. Landscaping services have been scheduled and will start soon. Site lighting wiring is progressing.

Last Updated 04.15.2024

+ CTA Life Extending Bus Overhaul - 430 Standard (1000 Series) Rolling Stock Bus $6,737,430 $6,737,430 On Schedule

Project Details

Description
Life Extending Overhaul - Up to 430 Standard (1000 Series) - This project will overhaul the engine and other major sub-components to provide the minimal amount of work necessary to keep the fleet going. By end of FY2020 630 buses will have met their estimated 12 year life expectancy. This extension would extend the bus life by four years. The life extension for the 40 foot 1000-1629 New Flyer Bus is essential to keeping a majority of the CTA fleet running in optimal condition. The current fleet of 40 foot NF buses is over 1000 buses. This project is essential to meet availability requirements for CTA. These buses were purchased in 2006-2007 and this life extension is essential to maintaining peak availability requirements at all 7 bus garages.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $6,737,430 $0 $6,737,430
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $25,100,429 $6,737,430 $0 $31,837,859

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,893,610
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The CTA Team drafted technical specs and project scope are under review as of this reporting period. The team completed testing the pilot Haldex air dryers on two buses and the buses were put back in service. The Team continues to complete the project independent cost estimate and release the updated specifications to the Purchasing Department to start the bid review/release process.

Last Updated 12.14.2023

+ Pace Computer Systems - Hardware & Software Support Facilities & Equipment Bus $0 $0 On Schedule

Project Details

Description
Computer Systems/Hardware & Software - Projects in 2021 include upgrades, licenses, and training for Hastus route-scheduling software, RideCheck ridership data software, ArcGIS software, and the Pace website. Procurement of digital screens for the interior of buses is also included.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,100,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is underway, and Pace executed a contract for redesigning Pace’s website. Activity continued with a rebid for the procurement of digital screens for the interior of the buses due to low responses. Additional tasks will be added throughout the duration of this project.

Last Updated 12.14.2023