Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.
Priority Projects have been identified by the Service Boards. These priority projects are updated on an annual basis. This page shows details about the funding for each priority project.
The 2024-2028 5-Year Regional Capital Program includes over 250 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2024-2028 Regional Capital Program. Beginning with the 2024-2028 Capital Program, projects are evaluated based on 15 measures which were identified in the new Regional Transit Strategic Plan, Transit is the Answer. All projects in the 2024-2028 program show the detailed evaluations in this site.
The metrics include evaluations of Equity and Accessibility which are used in the performance-based allocation process. The region has committed to dedicating 20% of programmed funds to projects that fulfill the regional goals of improving equity and accessibility for 2025 and beyond as a part of the new performance-based capital allocation process
The Service Boards have met and exceeded the 20% goal for the 2025-2028 budget years.
Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.
Replacement of buses reaching useful life (CNG and OTR Coach)
Project Title
Asset Category
Mode
2024 Funding
2024-2028 Funding
PMO
+
Purchase 40' Diesel Buses
Rolling Stock
Bus
$0
$0
✔︎
Project Details
Description
Replacement diesel buses (40') - Pace plans to replace 78 diesel buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections).
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$41,786,531
On Budget
On Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
Pace placed an order for the delivery of a total of 85 buses. To date, all 85 buses have been received and are in service. The buses are expected to service the routes currently serviced by West Division. This will be the final update on this project.
Last Updated 12.14.2023
+
Fixed Route CNG Buses
Rolling Stock
Bus
$0
$0
Project Details
Description
Replacement CNG buses - Pace plans to replace 115 diesel buses with 40' Compressed Natural Gas (CNG) buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for the future Northwest Division garage in Wheeling, currently being designed as a CNG fueling facility.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$28,050,000
$0
$0
$28,050,000
Last Updated 12.16.2022
+
Purchase 30' Diesel Buses
Rolling Stock
Bus
$0
$0
✔︎
Project Details
Description
This project is a new contract awarded in September 2019 for a new five?yearindefinite delivery/indefinite quantity contract for 30’ low floor diesel buses. Theminimum quantity to be purchased under this contract is 67 buses and the totalnumber of buses procured will not exceed the maximum amount of 164.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$80,261,908
On Budget
On Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
A total of 67 buses have been ordered to date. The first order consisted of 23 buses, all of which are in service. These were delayed due to the COVID-19 crisis. The second order consisted of 44 buses. All of the buses under the second order were received, with the final bus delivered in February 2023. The buses service the areas currently serviced by Fox Valley and Batavia. Pace will not pursue purchasing anymore buses under this contract. This will be the final update on this project.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$75,896,625
On Budget
On Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
Pace awarded a new contract for the purchase of additional vehicles in March 2022. The first order was a quantity of 47 CNG buses. The production of these vehicles has been put on hold during this reporting period. A portion of these vehicles will be utilized at the Northwest Wheeling Garage, which is an ongoing project. As Pace establishes a construction schedule for the Wheeling Garage, a production scheduled will be developed for the order of 47 buses.
Last Updated 12.14.2023
+
Pace
Improve Passenger Facilities - Park-n-Ride Lots
Bus
$0
$0
$6,250,000
$6,250,000
Updates and repairs to Park-n-Ride lots
Project Title
Asset Category
Mode
2024 Funding
2024-2028 Funding
PMO
+
I-55 Park-n-Rides
Stations & Passenger Facilities
Bus
$0
$0
Project Details
Description
I-55 Park-n-Rides: A/E design and expansion of existing (Bolingbrook, Burr Ridge, Romeoville) and/or construction of new park-n-ride facility.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$6,750,000
$0
$0
$6,750,000
Last Updated 12.16.2022
+
Bolingbrook Park-n-Ride
Stations & Passenger Facilities
Bus
$0
$0
Project Details
Description
This project will provide for improvements at the Bolingbrook Park-n-Ride
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Improvements to Transportation and Transfer Facilities
Project Title
Asset Category
Mode
2024 Funding
2024-2028 Funding
PMO
+
Improve Passenger Facilities
Stations & Passenger Facilities
Bus
$0
$0
Project Details
Description
Improve Passenger Facilities - Fabrication of a new Ventra machine for the O'Hare multimodal facility in 2021. Future renovations are being evaluated for Burr Ridge & Hillside Park-n-Rides, Chicago Heights Transfer Center, Riverdale Bus Turnaround, and Gurnee Mills Transportation Center.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$120,000
$0
$0
$120,000
Last Updated 12.16.2022
+
Joliet Gateway Center - Bus Stop Improvements
Stations & Passenger Facilities
Bus
$0
$0
✔︎
Project Details
Description
The City of Joliet is redeveloping the existing publicly owned Joliet Union Depot and nearby publicproperties as a Multi-Modal Transportation Center to be owned by the City. As part of this redevelopmentthe City of Joliet has partnered with Pace to construct a new Bus Station and turn-around for public andinter-city transit which will include parking improvements and the construction of new vehicular andpedestrian access and circulation system. The new Bus Station is south of New Street, north of MarionStreet and west of the BNSF/Union Pacific Railroad. The bus station will have 13 berths, with Pacehaving exclusive use of 11 berths, passenger loading islands with canopies and shelters, signage andlandscaping. There will also be a widening of the St. Louis Street, Pace bus operator and public toilets ata location immediately northeast of the existing Pace Heritage Division garage, and ADA accessiblesidewalks.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$9,509,500
On Budget
Behind Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
The City of Joliet and Pace entered into an Intergovernmental Grant Agreement for this project. The overall Joliet Gateway Terminal project is being managed by the City of Joliet. The City of Joliet prepared 100% design and bid the larger Intermodal Transportation Project, of which the Bus Turnaround Component is a part of. A construction contract was awarded, notice to proceed was issued in February, and construction began in March. Substantial completion and beneficial occupancy for the depot building was achieved in December 2021, after a walk?through inspection of depot building. The Scott Street pedestrian tunnel was completed in April 2022. Punch list items on building, passenger platforms and site landscaping were completed in June 2022.
Last Updated 12.14.2023
+
Harvey Transportation Center - Pace
Stations & Passenger Facilities
Bus
$0
$0
Project Details
Description
Pace is partnering with Metra, the City of Harvey, and IDOT with the intent to move the transportation center and combine it with the Metra station.The elements of the construction may include pavement, lighting, platforms, shelters, restrooms, structures and systems and may have a taxi release area to create a multimodal facility.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$30,850,000
$0
$0
$30,850,000
Last Updated 12.16.2022
+
Pace
IBS Replacement & Onboard Digital Screens
Bus
$0
$0
$32,150,000
$32,150,000
Equipment for bus tracking, communications, and data
Project Title
Asset Category
Mode
2024 Funding
2024-2028 Funding
PMO
+
Intelligent Bus System (IBS)
Electrical, Signal & Communications
Bus
$0
$0
✔︎
Project Details
Description
Intelligent Bus System - Project includes replacement Automatic Passenger Counter equipment (450), routers (600), Apollo cameras (650), IBS servers (8) & software, Storage Area Networks (2), dispatch radios (22), mobile radios (70), Integrated Vehicle Logic Unit Mobile Data Terminals (800), Tate data radios (800), Motorola voice radios (800), and data tower Radio Network Controller equipment (11).
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,250,000
$0
$0
$2,250,000
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$2,250,000
On Budget
Behind Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
Pace began activity of this project during this reporting period. This will be for automatic passenger counters on fixed route buses. Activities have just started and expected to ramp up in Q1-2024.
Last Updated 12.14.2023
+
Pace
Paratransit Vehicles - Expansion
Bus
$0
$0
$13,000,000
$13,000,000
New Dial-a-Ride and ADA vehicles for aging population
+
Pace
Paratransit Vehicles - Replacement
Bus
$1,801,859
$31,094,850
$86,508,000
$55,413,150
Replacement of vehicles reaching useful life
Project Title
Asset Category
Mode
2024 Funding
2024-2028 Funding
PMO
+
Purchase 15-passenger Paratransit Vehicles
Rolling Stock
Bus
$1,801,859
$31,094,850
✔︎
Project Details
Description
Paratransit Vehicles - Pace plans to purchase 298 replacement vehicles (22'-25' cutaway) including associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for paratransit services.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$1,801,859
$29,292,991
$31,094,850
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$7,388,134
$1,801,859
$29,292,991
$38,482,984
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$69,991,388
On Budget
On Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
These buses will service DuPage, Kane, Lake, Will and Cook counties. Pace awarded a new contract in November 2020. The first order was for a quantity of 210 paratransit buses. Chassis availability has delayed production. As of May, Pace has received the 152 vehicles and the remaining are in the final stages of production and aiming to deliver all buses by end of 2023. The second order of paratransit buses are ongoing and are expected to be executed in Q4-2023 for the community vehicle program.
Last Updated 12.14.2023
+
Electric Paratransit Vehicles
Rolling Stock
Bus
$0
$0
Project Details
Description
This project will fund the purchase of electric paratransit vehicles.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,000,000
$0
$0
$1,000,000
Last Updated 06.22.2023
+
Pace
Pedestrian Infrastructure/Shelters/Signs
Bus
$0
$0
$30,500,000
$30,500,000
Shelters, pedestrian access, and completion of conversion to posted stops
Project Title
Asset Category
Mode
2024 Funding
2024-2028 Funding
PMO
+
2021 - Bus Stop Shelters, Benches, Pads & Signs
Stations & Passenger Facilities
Bus
$0
$0
✔︎
Project Details
Description
Bus Stop Shelters - Engineering drawings, manufacture, and installation of bus stop shelters, concrete pads, and benches, including a heated bus shelter at the Waukegan Metra station.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$1,330,000
On Budget
Behind Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
Pace issued bids for construction of the pads and shelter installations and was awarded in this reporting period. Installation continues with this project where the previously ordered 10-15 shelters were received. The vendor will continue activities as assigned.
Last Updated 12.14.2023
+
2021 - Bus Tracker Signs
Stations & Passenger Facilities
Bus
$0
$0
✔︎
Project Details
Description
Bus Tracker Signs - Production of new electric signs and associated installation costs to provide real-time bus information to riders. In 2021, ten will be replacements for Pulse Milwaukee Line vertical markers, while an additional ten will be for new locations.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$600,000
On Budget
On Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
Activities continued related to the real time signs installed at various transit centers along the Pulse Milwaukee Line with various details on the specifics of screen size. Concurrently, real time bus information signage and electrical connections continued for various project elements. Permitting, installation, and invoicing continued as well.
Last Updated 12.14.2023
+
2020 - Bus Stop Shelters, Benches, Pads & Signs
Stations & Passenger Facilities
Bus
$0
$0
✔︎
Project Details
Description
Engineering drawings, manufacture, and installation of bus stop shelters, concrete pads, and benches, including a heated bus shelter at the Waukegan Metra station.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$1,550,000
On Budget
Behind Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
Pace issued bids for construction of the pads and shelter installations and was awarded in this reporting period. Installation continues with this project where the previously ordered 10-15 shelters were received. The vendor will continue activities as assigned.
Last Updated 12.14.2023
+
2020 - Bus Tracker Signs
Stations & Passenger Facilities
Bus
$0
$0
✔︎
Project Details
Description
Production of new electric signs and associated installation costs to provide real-time bus information to riders. In 2021, ten will be replacements for Pulse Milwaukee Line vertical markers, while an additional ten will be for new locations.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$750,000
On Budget
On Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
Activity for this project continued in this reporting period with real time bus information signage and electrical connections installed. Additional signs will be installed using other PAYGO funding for additional signs. This will be the final update on this project.
Last Updated 12.14.2023
+
2022 - Bus Stop Shelters, Benches, Pads & Signs
Stations & Passenger Facilities
Bus
$0
$0
✔︎
Project Details
Description
Bus Stop Shelters - Engineering drawings, manufacture, and installation of bus stop shelters, concrete pads, and benches, including a heated bus shelter at the Waukegan Metra station.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,125,000
$0
$0
$1,125,000
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$425,000
On Budget
On Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
Activities continued related to the real time signs installed at various transit centers along the Pulse Milwaukee Line with various details on the specifics of screen size. Concurrently, real time bus information signage and electrical connections continued for various project elements. Permitting, installation, and invoicing continued as well.
Last Updated 12.14.2023
+
2022 - Bus Tracker Signs
Stations & Passenger Facilities
Bus
$0
$0
Project Details
Description
Bus Tracker Signs - Production of new electric signs and associated installation costs to provide real-time bus information to riders. In 2021, ten will be replacements for Pulse Milwaukee Line vertical markers, while an additional ten will be for new locations.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$425,000
$0
$0
$425,000
Last Updated 12.16.2022
+
Pace
Pulse Infrastructure
Bus
$59,141,334
$59,141,334
$82,561,000
$23,419,666
Enhance Pulse service
Project Title
Asset Category
Mode
2024 Funding
2024-2028 Funding
PMO
+
Pulse Halsted
Stations & Passenger Facilities
Bus
$39,573,834
$39,573,834
Project Details
Description
Architectural/Engineering Design and Construction of stations, vertical markers, and other elements of the Pulse Halsted Arterial Rapid Transit Line. The project corridor consists of approximately 9 miles of South Halsted Street, from the Pace Harvey Transportation Center to 95th Street, and includes the segment of 95th Street that provides a connection to the CTA Red Line 95th/Dan Ryan station.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$32,137,334
$0
$32,137,334
State
$0
$7,436,500
$0
$7,436,500
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$500,000
$39,573,834
$0
$40,073,834
Last Updated 12.14.2023
+
Pulse 95th Street
Stations & Passenger Facilities
Bus
$19,567,500
$19,567,500
Project Details
Description
Design and construction of stations of the Pulse 95th Rapid Transit Line. The project corridor is approximately 12.4 miles in length and runs east-west between the CTA Red Line 95th/Dan Ryan Station in Chicago and Moraine Valley Community College in Palos Hills primarily routed along 95th Street, as well as several other roadways in Bridgeview, Chicago Ridge, Hickory Hills, and Palos Hills. The proposed line would include connections to other transit services including the CTA Red Line 95th/Dan Ryan Station and other CTA routes, other Pace bus routes, Metra Rock Island District Line Longwood Station, Metra Southwest Service, and Oak Lawn Patriot Station. As Pace’s third anticipated Pulse line, the 95th Street service will improve connectivity and increase transit service levels through higher frequencies, travel time savings, and station amenities. The Pulse 95th Street Line will connect to the Pulse Halsted Line, and eventually to the Pulse Harlem and Cicero Lines.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$15,654,000
$0
$15,654,000
State
$0
$3,913,500
$0
$3,913,500
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,464,000
$19,567,500
$0
$21,031,500
Last Updated 12.14.2023
+
Pace
Regional Transit Signal Priority (RTSP)
Bus
$0
$0
$34,685,929
$34,685,929
Expand Transit Signal Priority installations region-wide
Project Title
Asset Category
Mode
2024 Funding
2024-2028 Funding
PMO
+
Transit Signal Priority (TSP)
Electrical, Signal & Communications
Bus
$0
$0
✔︎
Project Details
Description
Transit Signal Priority Integration - TSP implementation along priority corridors as part of the Regional Transit Signal Priority Implementation Program. Pace plans to deploy TSP along nine additional corridors at approximately 300 signalized intersections. The corridors include: 159th Street, Sibley Boulevard/147th Street, Roosevelt Road, Cicero Avenue, 95th Street, Grand Avenue (Lake County), Cermak Road, I-90 Transit Corridor Access Intersections and Halsted Street. This form represents the portion of the project funded with PAYGO in 2024. Years 2021-2023 of TSP related projects are funded with ICE funds as shown in Exhibit I.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$4,314,071
$0
$0
$4,314,071
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$14,031,402
On Budget
On Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
The vendor received the permit to implement TSP system along 58 signalized intersections of Dempster Street from IDOT. Systems integration testing were completed at 47 of the 58 signalized Dempster intersections was completed and railroad crossings field tests/data analysis completed at various locations along Dempster. TSP installation along Dempster St. in Evanston is in process and will continue thru Q2-2023. The vendor completed construction and systems implementation along Grand Ave. in a previous but this quarter acquired IDOT District 1 approval and permitting for EOS deployment along Grand and other corridors. Deployment and initial testing of TSP along Roosevelt Rd. was completed and the vendor is currently demonstrating the information to IDOT Dist. 1. TSP deployment along 147th St. was completed and Pace acquired permits for 95th St. with construction continuing through 2023. Permit acquisition activities continues for Rand, Cermak, and 159th w
Last Updated 12.14.2023
+
Pace
Security, Computer, Software, and Office Systems Upgrades
Bus
$2,513,505
$10,513,505
$31,936,495
$21,422,990
Upgrade systems to provide enhanced asset protection and business systems
Project Title
Asset Category
Mode
2024 Funding
2024-2028 Funding
PMO
+
Computer Systems - Hardware & Software
Support Facilities & Equipment
Bus
$0
$0
✔︎
Project Details
Description
Computer Systems/Hardware & Software - Projects in 2021 include upgrades, licenses, and training for Hastus route-scheduling software, RideCheck ridership data software, ArcGIS software, and the Pace website. Procurement of digital screens for the interior of buses is also included.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$1,100,000
On Budget
On Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
This project is underway, and Pace executed a contract for redesigning Pace’s website. Activity continued with a rebid for the procurement of digital screens for the interior of the buses due to low responses. Additional tasks will be added throughout the duration of this project.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,398,000
$0
$0
$2,398,000
Last Updated 12.14.2023
+
Onboard Digital Screens
Support Facilities & Equipment
Bus
$2,513,505
$10,513,505
Project Details
Description
Purchase and install digital screens inside existing buses to display passenger information, such as next-stop announcements, detour notices, and passenger notices.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.