Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.
Priority Projects have been identified by the Service Boards. These priority projects are updated on an annual basis. This page shows details about the funding for each priority project.
The 2024-2028 5-Year Regional Capital Program includes over 250 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2024-2028 Regional Capital Program. Beginning with the 2024-2028 Capital Program, projects are evaluated based on 15 measures which were identified in the new Regional Transit Strategic Plan, Transit is the Answer. All projects in the 2024-2028 program show the detailed evaluations in this site.
The metrics include evaluations of Equity and Accessibility which are used in the performance-based allocation process. The region has committed to dedicating 20% of programmed funds to projects that fulfill the regional goals of improving equity and accessibility for 2025 and beyond as a part of the new performance-based capital allocation process
The Service Boards have met and exceeded the 20% goal for the 2025-2028 budget years.
Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.
Replacement of vehicles and radio systems for existing program. New vehicles, transfer locations and maintenance facilities for direct Pace ownership of assets for ADA service within City of Chicago
Project Title
Asset Category
Mode
2024 Funding
2024-2028 Funding
PMO
+
ADA Technology Upgrades and Transfer Centers
Systemwide
Bus
$0
$0
✔︎
Project Details
Description
Regional ADA Paratransit Communication Technology and Transfer Locations - Projects include upgrades to the Trapeze software, TripCheck online booking and tracking, TripCheck Interactive Voice Response phone system, text/email notifications, and Ventra integration. In areas with frequent transfers, funding will be used to purchase land, build facilities, and provide amenities for riders. Pace has identified a location that is adjacent to the Northwest Transportation Center in Schaumburg that is planned to be the first of these transfer locations.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$20,000,000
On Budget
On Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
A Notice to Proceed was issued in February 2023 for the construction of the Northwest Transportation Center ADA Transfer Facility. The MWRD permit was approved and construction fencing was installed for the west canopy demolition work. Similarly, the underground storm sewers and drainage structure installation were completed in the west parking lot area and have been connected to the existing storm sewers east of the bus driveway. The existing detention basin west of the bus driveway has been backfilled. The Issued for Construction (IFC) drawings are being revised by the designer based on comments from Pace. Progress continues on the implementation of various technology enhancement projects. The first two phases of the Taxi Access Program have been completed and the vendor is currently working on the third phase. Activity continues on two phases of Trapeze technology enhancements to Pace’s Trapeze paratransit scheduling system. Work has progressed on e
Last Updated 04.15.2024
+
Pace
Support Equipment/Non-Revenue Vehicles
Bus
$0
$0
$22,450,000
$22,450,000
Facility and system maintenance equipment and vehicles
Project Title
Asset Category
Mode
2024 Funding
2024-2028 Funding
PMO
+
Support Equipment - Non-Revenue Vehicles
Support Facilities & Equipment
Bus
$0
$0
Project Details
Description
Support Equipment/Non-Revenue Vehicles - Projects in 2021 include the purchase of 18 compact SUVs and one minivan with wheelchair ramp.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$400,000
$0
$0
$400,000
Last Updated 12.16.2022
+
CTA
Bus Garage Improvements
Bus
$0
$0
$248,090,000
$248,090,000
Provide repairs at bus maintenance garages and shops
Project Title
Asset Category
Mode
2024 Funding
2024-2028 Funding
PMO
+
Improve Facilities - Electric Bus Program Planning
Support Facilities & Equipment
Bus
$0
$0
Project Details
Description
CTA has committed to a full electrification of the bus fleet by 2040, providing significant air quality improvements to the region and the immediate vicinity of the garage facilities. To implement the program, the garages will need to be converted to allow for routing servicing / charging of the buses as well as new maintenance requirements. The work will generally involve significant electrical upgrades, installation of charger infrastructure, and general updates to the facility to support the conversion to an electric fleet.The primary locations for the electric charger upgrades will be within all of the CTA bus garages. Secondary locations will be on route charging at major terminals to support the longer bus routes. A study is ongoing to recommend network options and charging requirements. Additionally, load flow studies will be required at all of the garages to properly determine the specific charging needs.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$44,599,730
$0
$0
$44,599,730
Last Updated 12.16.2022
+
North Park Garage – Building Demolition
Support Facilities & Equipment
Bus
$0
$0
Project Details
Description
Project will cover the building demolition and site restoration of 5323 N. Kedzie.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$177,485
$0
$0
$177,485
Last Updated 12.16.2022
+
Bus Hoist Replacement Program
Support Facilities & Equipment
Bus
$0
$0
Project Details
Description
Project will support an updated assessment of the bus hoists to determine which may need replacement, as well as design and construction for those locations.This funding will provide for the purchase and installation of bus hoists at five CTA bus garages.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0
Last Updated 12.16.2022
+
CTA
Replacement Buses (4000 Series) - Electric Buses
Bus
$0
$183,375,355
$263,332,432
$79,957,077
Replace 208 Articulated Buses due replacement in 2023. Priced at FY 2021 Articulated e-bus @1.4M. Ongoing need to replace buses as they age.
Project Title
Asset Category
Mode
2024 Funding
2024-2028 Funding
PMO
+
Purchase Articulated Electric Buses and Charging Equipment
Rolling Stock
Bus
$0
$183,375,355
Project Details
Description
Funding will provide for a new procurement intended to replace 208 articulated 4000-Series buses with the equivalent number of electric buses
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$158,558,869
$158,558,869
State
$0
$0
$24,816,486
$24,816,486
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$29,336,647
$0
$183,375,355
$212,712,002
Last Updated 12.14.2023
+
CTA
Mid-Life Bus Overhaul (4300 series)
Bus
$0
$0
$0
$0
Overhauls to maintain vehicles, ensure reliability and enable to perform through full useful life
Project Title
Asset Category
Mode
2024 Funding
2024-2028 Funding
PMO
+
Mid-Life Bus Overhaul 4300 Series
Rolling Stock
Bus
$0
$0
✔︎
Project Details
Description
Overhauls of the 4300 articulated buses to maintain vehicles, ensure reliability and enable to perform through full useful life
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$9,615,472
$0
$0
$9,615,472
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$25,327,057
On Budget
Behind Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
The milestones related to accepting the two pilot buses was completed in November 2023. Work on Milestone 3 continues but is behind schedule. The CTA is waiting for NFI to submit a new Recovery Schedule that will demonstrate how the schedule will make up for the delays to the project to get it back on schedule. A new Recovery Schedule is expected by the next reporting period.
Last Updated 04.15.2024
+
CTA
Rail Car Maintenance Activities
Rail
$0
$0
$300,000,000
$300,000,000
Preform rail car maintenance activities to keep the fleet in a state of good repair.
Project Title
Asset Category
Mode
2024 Funding
2024-2028 Funding
PMO
+
2022 - Rail Car Maintenance
Rolling Stock
Rail
$0
$0
✔︎
Project Details
Description
CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle. When certain maintenance tasks are needed to repair or replace a component before it reaches its end of useful life and fails with an increased frequency, specific component campaign work is conducted.The major systems that must be maintained on CTA’s rail cars include the following:Propulsion, Safety, HVAC, Braking, Battery/Charging, Signage, Doors, Windows, Traction Power, RCA, Lighting, Automatic Train Control, Communication , Suspension, Car body/Structure. CTA’s Rail Terminal Shops are responsible for the maintenance that may result in replacement of a variety of components such as: traction motors, HVAC components and packages, lights, public address system components, trucks, wheels assemblies, hydraulic units, couplers, drawbars, and numerous other mechanical and electrical components. CTA’s Heavy Maintenance Shop is responsible for the rebuild/repair/manufacture of components for the railcar fleet such as wheel assemblies, truck assemblies, traction motors, air comfort units, electronic devices, control units, and associated devices including solid state and microprocessor-controlled units.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$18,106,390
$0
$0
$18,106,390
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$18,106,390
On Budget
On Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
Rail car maintenance activities for this project are on hold until prior year projects are completed. Major elements will include, but are not limited to, rail car inspection and engineering, vehicle wiring, and body work.
Last Updated 12.14.2023
+
2020 - Rail Car Maintenance
Rolling Stock
Rail
$0
$0
✔︎
Project Details
Description
CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle. When certain maintenance tasks are needed to repair or replace a component before it reaches its end of useful life and fails with an increased frequency, specific component campaign work is conducted.The major systems that must be maintained on CTA’s rail cars include the following:Propulsion, Safety, HVAC, Braking, Battery/Charging, Signage, Doors, Windows, Traction Power, RCA, Lighting, Automatic Train Control, Communication , Suspension, Car body/Structure. CTA’s Rail Terminal Shops are responsible for the maintenance that may result in replacement of a variety of components such as: traction motors, HVAC components and packages, lights, public address system components, trucks, wheels assemblies, hydraulic units, couplers, drawbars, and numerous other mechanical and electrical components. CTA’s Heavy Maintenance Shop is responsible for the rebuild/repair/manufacture of components for the railcar fleet such as wheel assemblies, truck assemblies, traction motors, air comfort units, electronic devices, control units, and associated devices including solid state and microprocessor-controlled units.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$27,074,655
On Budget
Behind Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
Rail car maintenance activities with this funding were completed in this reporting period. Final invoices remain. This will be the final update on this project.
Last Updated 12.14.2023
+
2021 - Rail Car Maintenance
Rolling Stock
Rail
$0
$0
✔︎
Project Details
Description
CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle. When certain maintenance tasks are needed to repair or replace a component before it reaches its end of useful life and fails with an increased frequency, specific component campaign work is conducted.The major systems that must be maintained on CTA’s rail cars include the following:Propulsion, Safety, HVAC, Braking, Battery/Charging, Signage, Doors, Windows, Traction Power, RCA, Lighting, Automatic Train Control, Communication , Suspension, Car body/Structure. CTA’s Rail Terminal Shops are responsible for the maintenance that may result in replacement of a variety of components such as: traction motors, HVAC components and packages, lights, public address system components, trucks, wheels assemblies, hydraulic units, couplers, drawbars, and numerous other mechanical and electrical components. CTA’s Heavy Maintenance Shop is responsible for the rebuild/repair/manufacture of components for the railcar fleet such as wheel assemblies, truck assemblies, traction motors, air comfort units, electronic devices, control units, and associated devices including solid state and microprocessor-controlled units.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$10,000,000
On Budget
On Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
Rail car maintenance activities are ongoing. Major elements include, but not limited to, rail car inspection and engineering; vehicle wiring; and body work. The project budget has been decreased via a grant amendment for a bus maintenance project.
Last Updated 12.14.2023
+
CTA
Replacement Bus Purchase (4300 series) - Electric Buses
Rail
$0
$0
$140,000,000
$140,000,000
Ongoing need to replace diesel articulated buses as they age with electric buses.
+
CTA
Blue Line (O'Hare) Traction Power Capacity & Track Improvements
Rail
$0
$0
$215,740,272
$215,740,272
Upgrades and State of Good Repair projects along the O'Hare Branch of the Blue Line
Project Title
Asset Category
Mode
2024 Funding
2024-2028 Funding
PMO
+
Blue Line O'Hare Branch Traction Power Improvements
Track & Structure
Rail
$0
$0
✔︎
Project Details
Description
Blue Line O'Hare Branch Traction Power Improvements GTT - Project will include targeted track repairs to remove existing slow zones on the Congress Branch of the Blue Line. CTA has identified traction power voltage drop issues along the Blue Line. Scope of work will include but not limited to the following elements: New infill substations, infill wayside energy storage systems, infill tie houses, third rail replacement, addition of auxiliary negative rail; work will be performed by an outside contractor. In addition project will aslo provide for the replacement of ties, track fasteners, footwalks, and incidental signal and traction power; this part of work will be performed by CTA Field Forces.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$12,405,159
$0
$0
$12,405,159
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$207,100,000
On Budget
On Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
The contractor completed installation and testing of wayside signal equipment and all cutovers along the specific portion of the blue line. The project is considered substantially complete with the contractor performing punch list items. Final invoices remain and this will be the final update on this project.
Last Updated 12.14.2023
+
Blue Line Traction Power - Barry, Damen and Canal
Track & Structure
Rail
$0
$0
✔︎
Project Details
Description
Construct a tie house (at the intersection of Milwaukee/Canal/Lake Street) and two new substations (atBarry/Kimball intersection and Damen/Milwaukee intersection) to support traction power needs on theBlue Line. These assets will support increasing ridership demands as well as the power needed tosupport 5000 and 7000 series rail cars. The location of the tie house and substations were determinedby the Blue Line Load Flow study, which identified areas that were likely to experience traction powerissues.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,200,191
$0
$0
$2,200,191
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$122,417,171
On Budget
Behind Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
The contractor during this reporting worked out of sequence to reduce the delays to the project. Construction continues at Damen, Barry and Canal Tie House. Community notices are being put together for the Haymarket elevated work, which includes installing and testing the grounding system as well as steel mesh installation at track level. ComEd coordination meetings have begun for power sources.
Last Updated 04.15.2024
+
Blue Line O'Hare Branch - Special Trackwork
Track & Structure
Rail
$0
$0
Project Details
Description
Funds provide for the replacement of stock rails, switch points, frogs, switch ties, and plates on the O’Hare Line that are no longer in a state of good repair and require concentrated maintenance by CTA forces to ensure service. The component replacement will take place between the Jefferson Park interlocking and the O’Hare terminal.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,013,674
$0
$0
$2,013,674
Last Updated 12.16.2022
+
Traction Power Upgrades - Kedvale, Edmunds & Sacramento Substations
Track & Structure
Rail
$0
$0
✔︎
Project Details
Description
This project will Provide for AC breaker replacement at Kedvale, Edmunds and Sacramento substations. This will also include the replacement of oil (non?PCB) transformer and rectifiers along with roof and doors replacement at the Kedvale and Sacramento substations.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$12,030,427
On Budget
On Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
The contractor was able to install the transformers, rectifiers, as well as roof and door replacements since the last reporting period. The project reachedsubstantial completion in January 2023 and punchlist items were completed. Final invoices remain. This will be the final update on this project.
Last Updated 12.14.2023
+
Old Mannheim Replacement Foot walk
Track & Structure
Rail
$0
$0
Project Details
Description
Restore footwalk at Old Manheim on the O'Hare Line.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$250,000
$0
$0
$250,000
Last Updated 12.16.2022
+
CTA
Blue Line Forest Park Modernization - Phase 1
Rail
$0
$0
$131,245,158
$131,245,158
Track improvements to address the most immediate critical track needs on the Forest Park Branch to enable its continued operation
Project Title
Asset Category
Mode
2024 Funding
2024-2028 Funding
PMO
+
Forest Park: Phase 1 - Trackwork Halsted to IMD
Track & Structure
Rail
$0
$0
✔︎
Project Details
Description
The CTA's Forest Park Blue Line Upgrades Project is the first of four phases of the Forest Park Branch. This project will provide for new trackwork from Halsted to Illinois Medical District (IMD), an accessible station at Racine, advanced utility work, and a new substation and traction power equipment upgrades at Hermitage. This work will enhance service quality via speed, reliability, and comfort, and improve operational efficiency on the Forest Park Branch of CTA's rapid transit Blue Line service.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$43,497,351
$0
$0
$43,497,351
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$124,596,980
On Budget
Ahead of Schedul
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
The contractor submitted a request for substantial completion for the date of 12/8/23. CTA has performed a walkthrough and generated a punchlist. Contractor continues with punchlist work. Fence enclosure, barrier wall, and downspouts were completed. Fiber optic splicing and testing is ongoing.
Last Updated 04.15.2024
+
Forest Park: Phase 1 - Racine Station and Morgan Substation & Hermitage Traction Power Improvements
Track & Structure
Rail
$0
$0
✔︎
Project Details
Description
The CTA's Forest Park Blue Line Upgrades Project is the first of four phases of the Forest Park Branch. This project will provide for new trackwork from Halsted to IMD, an accessible station at Racine, advanced utility work, and a new substation and traction power equipment upgrades at Hermitage. This work will enhance service quality via speed, reliability, and comfort, and improve operational efficiency on the Forest Park Branch of CTA's rapid transit Blue Line service.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$67,471,237
$0
$0
$67,471,237
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$97,080,000
On Budget
On Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
FHP heavy mobilization is expected to begin in late April 2024 at the new laydown location at Leavitt and Lake. Heavy mobilization is expected to involve FHP’s construction materials, construction trailers and equipment.
FHP plans on having their first 54-hour line cut that is scheduled for April 26, 2024, with May 3, 2024, being a backup date as contingency. During this line cut, FHP expects to perform steel erection at Racine Station and Morgan house. FHP has requested a TAO (Track Access Occurrence) that allows manpower to work without ROW (Right of Way) training due to the complete power shut down and no train service in the work zone. The line cut work zone will extend between UIC Halsted and IMD and will be supported by CTA bus shuttles in the area. The dates are contingent on steel fabrication and submittal approvals. Morgan steel fabrication is in the final stages and currently undergoing the galvanizing stage. Racine is currently being fabr
Last Updated 12.14.2023
+
Forest Park: Phase 1 - Advance Utility
Track & Structure
Rail
$0
$0
✔︎
Project Details
Description
The CTA's Forest Park Blue Line Upgrades Project is the first of four phases of the Forest Park Branch.This project will provide for new trackwork from Halsted to IMD, an accessible station at Racine,advanced utility work, and a new substation and traction power equipment upgrades at Hermitage. Thiswork will enhance service quality via speed, reliability, and comfort, and improve operational efficiency onthe Forest Park Branch of CTA's rapid transit Blue Line service.
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source
Previous Funding*
2024 Funding
2025-2028 Funding
Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
End Date
$3,396,000
On Budget
On Schedule
^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
The contractors for all four surveys completed their work during this reporting period and two are in final comments. Invoicing continues and all four contracts are considered to be in financial closeout. This will be the last update on this project.